Former Gas Station Marlborough, MA

Project Highlights:

– 5 Underground Storage Tanks

– Construction dewatering and groundwater treatment

– Excavation, Stockpiling, Transportation, and Disposal of soils

– Backfill and restoration

– MA DEP oversight

 

Summary of project

TRIDENT Environmental Group, LLC was selected to clean and remove five underground storage tanks formerly containing various petroleum products. Contaminated soils were excavated, stockpiled, loaded into trucks and transported for disposal. Site access and conditions were tight. Ground water management was implemented to control the season high water table during the tank removals.